Vendor Modernization RAID Log

Please find Key RAID Log as part of Vendor modernization: Detailed Raid log

Summary

Sr.NoDateDescriptionIssue TypeOwnersTarget end Dt.Issue Statusremarks/comments/Decision
121-Mar"Suspended” state for Vendor needs to be considered as part of requirementDecisionJaya21-MarClosedAgreed and to be included in BRD. Details to be added in JIRA story
221-Mar“Timeline feature” – the same can be achieved using Audit trialDecisionJaya, Tech team21-MarClosedAligned on 21/March
320-MarReview of Finance attributes with SAP systemsRiskJaya26-MarClosed20/March: Shared attributes and data model artifacts with the team by Jaya. Follow up call setup on 26/March to close open items26/March:
418-MarDecision pending on ownership of UIRiskSameera, Anita, PraveenIn Progress07/Oct: Alignment planned with Laurence during week of 7/October for securing UI development resources.21/Mar: Risk has been raised with Leadership team regarding ownership of UI. Awaiting for decision to be taken.
518-MarBRD Open Points to closure (https://my.maerskgroup.com//r/personal/chetan%5Fverma%5Fmaersk%5Fcom/%5Flayouts/15/doc2.aspx?sourcedoc=%7B03dd29b7-d771-4909-8e7b-39ce1fa4ba8c%7D&action=edit&activeCell=%27VMDM%20-%20BRD%20Open%20Topics%27!G3&wdinitialsession=72b529e2-725f-5e1d-ba51-e8469f12b5c1&wdrldsc=9&wdrldc=1&wdrldr=AccessTokenExpiredWarningOrgPolicyRestriction%2CRefr)Jaya, Praveen, AjitClosed21/March: Identified key open points as part of workshop. Working towards closure of the open points as part of multiple refinement sessionsBRD sign off has been received.
6Integration with Keelvar, MinervaDecisionJaya, Praveen, AjitClosedNot a part of MVP 1. Minerva not in scope for Yr 2024.
720-MarHistory & Audit trail would be reused from Customer with attributes of VendorDecisionJaya, Praveen, AjitClosed20/Mar: existing customer UI layout, features for History and Audit would be reused for Vendor
824-SeptTrade Automation to be replaced by MinervaInformationAjit LawhateClosedMinerva on temporary basis will integrate to OnPrem SMDS, once Retina integration is available they will move to Retina.
924-SeptGLSMInformationGovind ThakurClosedGLSM will also consume over SMQ on temporary basis till Retina integration is available
10Identification of Tech Team resource to initiate Development phaseRiskAjit, SumeetIn ProgressNeed to Identify & form development team.
1126-SeptIntegration with SCPDependencyEka, ItishaIn ProgressEka, Itisha to come back post review of BRD and Attributes definition file to confirm it is meeting SCP expectations. In case of ambiguity, alignment to be planned with Vendor MDO.Request for securing timeline and resources as part of SCP OP prioritization has been highlighted.