Vendor Modernization RAID Log
Please find Key RAID Log as part of Vendor modernization: Detailed Raid log
Summary
| Sr.No | Date | Description | Issue Type | Owners | Target end Dt. | Issue Status | remarks/comments/Decision |
|---|---|---|---|---|---|---|---|
| 1 | 21-Mar | "Suspended” state for Vendor needs to be considered as part of requirement | Decision | Jaya | 21-Mar | Closed | Agreed and to be included in BRD. Details to be added in JIRA story |
| 2 | 21-Mar | “Timeline feature” – the same can be achieved using Audit trial | Decision | Jaya, Tech team | 21-Mar | Closed | Aligned on 21/March |
| 3 | 20-Mar | Review of Finance attributes with SAP systems | Risk | Jaya | 26-Mar | Closed | 20/March: Shared attributes and data model artifacts with the team by Jaya. Follow up call setup on 26/March to close open items26/March: |
| 4 | 18-Mar | Decision pending on ownership of UI | Risk | Sameera, Anita, Praveen | In Progress | 07/Oct: Alignment planned with Laurence during week of 7/October for securing UI development resources.21/Mar: Risk has been raised with Leadership team regarding ownership of UI. Awaiting for decision to be taken. | |
| 5 | 18-Mar | BRD Open Points to closure (https://my.maerskgroup.com/❌/r/personal/chetan%5Fverma%5Fmaersk%5Fcom/%5Flayouts/15/doc2.aspx?sourcedoc=%7B03dd29b7-d771-4909-8e7b-39ce1fa4ba8c%7D&action=edit&activeCell=%27VMDM%20-%20BRD%20Open%20Topics%27!G3&wdinitialsession=72b529e2-725f-5e1d-ba51-e8469f12b5c1&wdrldsc=9&wdrldc=1&wdrldr=AccessTokenExpiredWarningOrgPolicyRestriction%2CRefr) | Jaya, Praveen, Ajit | Closed | 21/March: Identified key open points as part of workshop. Working towards closure of the open points as part of multiple refinement sessionsBRD sign off has been received. | ||
| 6 | Integration with Keelvar, Minerva | Decision | Jaya, Praveen, Ajit | Closed | Not a part of MVP 1. Minerva not in scope for Yr 2024. | ||
| 7 | 20-Mar | History & Audit trail would be reused from Customer with attributes of Vendor | Decision | Jaya, Praveen, Ajit | Closed | 20/Mar: existing customer UI layout, features for History and Audit would be reused for Vendor | |
| 8 | 24-Sept | Trade Automation to be replaced by Minerva | Information | Ajit Lawhate | Closed | Minerva on temporary basis will integrate to OnPrem SMDS, once Retina integration is available they will move to Retina. | |
| 9 | 24-Sept | GLSM | Information | Govind Thakur | Closed | GLSM will also consume over SMQ on temporary basis till Retina integration is available | |
| 10 | Identification of Tech Team resource to initiate Development phase | Risk | Ajit, Sumeet | In Progress | Need to Identify & form development team. | ||
| 11 | 26-Sept | Integration with SCP | Dependency | Eka, Itisha | In Progress | Eka, Itisha to come back post review of BRD and Attributes definition file to confirm it is meeting SCP expectations. In case of ambiguity, alignment to be planned with Vendor MDO.Request for securing timeline and resources as part of SCP OP prioritization has been highlighted. |